Standby generator and transfer switch

Standby generator and transfer switch permit in San Antonio, TX

City of San Antonio, Texas · Official sources verified November 28, 2026 (America/Chicago)

Quick answer

In San Antonio, a home standby generator is permitted by the Development Services Department (DSD) through the BuildSA portal. DSD’s Information Bulletin 250 (revised October 1, 2026) says any back-up system application should use the SOLAR permit type, which is a subtype of the general electrical permit and allows plan uploads. New electrical work must be done by a Texas-licensed electrical contractor and master electrician who is registered with DSD, and CPS Energy (the only utility serving the city) has its own distributed generation review and commissioning step. The FY 2027 Development Fee Schedule lists UPS/generator fees by kilowatt size band, starting at $1.84 (1–5 kW) and $3.74 (6–50 kW), plus a $57.50 electrical permit base fee in the existing-residential table. DSD’s residential page says homeowners must use licensed trade contractors for new electrical work.

Yes — electrical permit (BuildSA SOLAR type) for any back-up system

Do I need a permit?

IB 250 says that for any back-up system installation you select the SOLAR permit type in the BuildSA portal; it is a subtype of the general electrical permit. IB 250 defines eligible home backup power as generators and associated transfer switches, energy storage, and solar with storage, connected at 600 volts or less, serving one- and two-family dwellings. It lists items outside the third-party route: fuel gas connections and piping (separate plumbing permit), electric service or panelboard repairs, replacements or upgrades (separate electrical permit), unrelated feeders and branch circuits, and EV outlets and circuits. IB 250 also says a back-up system may not be used until all required inspections are done, including DSD inspections such as service upgrades and gas inspections for natural gas generators, and until CPS Energy commissioning requirements are met. DSD’s FY 2027 fee schedule and the City’s residential permits page do not list a separate generator-only permit type beyond this electrical/SOLAR process.

No — new electrical work must go through a licensed, DSD-registered electrical contractor

Can a homeowner pull it?

The City’s Residential Permits page says that while a homeowner can perform many types of non-structural work, “for your safety you must use licensed trade contractors for new electrical, plumbing and/or HVAC project components.” Its homeowner permit chart does not include electrical, and its Trade Contractor section lists electrical permits as obtainable by trade contractors licensed by the City or State and registered with the City. DSD’s electrical page says a State Electrical License must be registered with DSD to receive a permit, and IB 250 requires the installing business to hold a Texas Electrical Contractor’s license and a Texas Master Electrician’s license from TDLR. The Texas Department of Licensing and Regulation says anyone who performs non-exempt electrical work in Texas must be licensed and work through a licensed electrical contractor. Third-party plan review and inspection under IB 250 must come from someone independent of the installing contractor: a master electrician, an electrical inspector or a Texas-licensed engineer. This page does not research any state-law exemptions; ask DSD at 210-207-1111 if you think one applies.

Official AHJ office

Office
City of San Antonio — Development Services Department (DSD)
Division
Inspections / Electrical permits
Address
Cliff Morton Development and Business Services Center (One Stop), 1901 S. Alamo St., San Antonio, TX 78204
Phone
210-207-1111
Email
[email protected]
Hours
Monday–Friday, 7:45 a.m. to 4:30 p.m. (City DSD pages). Customer Service 3-1-1 or 210-207-6000.
Portal
BuildSA Customer Portal

DSD permits work inside San Antonio city limits. Properties in unincorporated Bexar County or other cities are different jurisdictions. DSD hours posted on its pages: Monday–Friday, 7:45 a.m.–4:30 p.m.

More official contacts

Fees

The FY 2027 Development Fee Schedule (revised October 2026) lists a UPS/Generator/Distributed Generation/Storage Batteries line in the electrical section by size band. The schedule’s existing-residential electrical table also has a $57.50 permit base fee, service-rating fees, and other per-item fees. The schedule does not give a worked generator example, and it is not stated whether the per-kW rate applies across all kW or to the size band; ask DSD for a quote or see the fee line under your application in BuildSA.

ItemAmountSource note
Electrical permit base fee (commercial and existing residential) $57.50 FY 2027 fee schedule, electrical section.
Generator / UPS / distributed generation / storage batteries, 1–5 kW $1.84 FY 2027 fee schedule; unit basis (per kW) as listed in the schedule’s size-band table.
Generator / UPS / distributed generation / storage batteries, 6–50 kW $3.74 FY 2027 fee schedule. Most residential standby units fall in this band.
Generator / UPS / distributed generation / storage batteries, 51–300 kW $5.58 FY 2027 fee schedule.
Generator / UPS / distributed generation / storage batteries, over 301 kW $7.48 FY 2027 fee schedule.
Service rating fee, 0–200 amps (if a service change is part of the job) $3.74 FY 2027 fee schedule.
Work with CPS fee (if a CPS outage is needed) $2.47 FY 2027 fee schedule; IB 250 says to select Work with CPS if an outage is required.
Electrical plan review fee $115.00 Fee schedule special services. IB 250 says the plan review fee is not assessed on third-party reviewed submittals.
Re-inspection fee $57.50 FY 2027 fee schedule, electrical special services.
Inspection schedule fee $3.45 Schedule says it is free if scheduled online.
Surcharges and payment fees 4% + 4%; $11.50; 3% Schedule disclaimer: unless noted, fees carry a 4% Technological Improvement and a 4% Development Services surcharge; applications not submitted through the online portal carry an $11.50 convenience fee; credit cards add 3%.
Natural gas piping plumbing permit Not researched here IB 250 says gas piping needs a separate plumbing permit; see the fee schedule’s plumbing section or ask DSD.

Fees are from the FY 2027 Development Fee Schedule (revised October 2026) as fetched on November 28, 2026. The final charge depends on the line items selected on your application. Confirm in BuildSA or with DSD before paying.

FY 2027 Development Fee Schedule (revised October 2026)

How to apply

  1. Confirm the address is inside San Antonio city limits and that CPS Energy is your electric utility (IB 250 says CPS Energy is the only utility serving the city).
  2. Hire an electrical contractor that holds a Texas Electrical Contractor’s license and a Texas Master Electrician’s license from TDLR and is registered with DSD.
  3. Send the CPS Energy distributed generation package. IB 250 says back-up generator applications go by PDF email to [email protected] with a one-line diagram, site plan and elevation; it is preferred to have CPS approval first, but you may submit to CPS and the City at the same time.
  4. Open a BuildSA account and, under the Building module, create a SOLAR permit type for the back-up system. Fill in the electronic application, select Work with CPS if an outage is needed, and pay the fee as part of the application.
  5. Upload the plan set (signed and sealed by a Texas master electrician or engineer) with the signed Third-Party Review Declaration and the Hold Harmless and Indemnity Agreement if you use third-party review under SB 1202. IB 250 says DSD responds within two business days, unless historic preservation or stormwater review is triggered.
  6. Do not start work until a full permit is issued; IB 250 says the permit record is created with a different number than the application. Pull separate permits for gas piping and for any service or panel upgrade.

Inspections

  1. Under IB 250, projects with third-party plan review must have third-party inspections. The third-party professional completes all backup-system inspections and uploads the signed Third-Party Inspection Declaration of Compliance and Liability to the permit.
  2. A DSD electrical inspector reviews the submitted information and clears the inspections so a release goes to CPS Energy for commissioning.
  3. DSD inspectors still perform inspections for items outside the third-party scope, such as service replacements or upgrades and gas inspections for natural gas generators.
  4. IB 250’s plan requirements include a dimensioned site plan with generator location and property-line setbacks, a main electrical service elevation, a one- or three-line diagram, load calculations under 2023 NEC Article 220, manufacturer specification sheets, and labeling information. It also says a 36-inch diagonal clearance is required from the gas meter to any electrical equipment, including receptacles.
  5. IB 250 lists the applicable codes as the 2023 National Electrical Code, the 2024 IRC, IFC, IMC and IPC, and San Antonio’s Chapter 10 Building Related Codes. It does not list generator-to-structure setback distances beyond those plan requirements; check the manufacturer’s instructions and ask DSD.

Common pitfalls

Questions people actually ask

Do I need a permit for a standby generator in San Antonio?

Yes. DSD’s IB 250 says to apply through the BuildSA portal using the SOLAR permit type for any back-up system, and work may start only after a full permit is issued.

Can I install the generator myself and pull the permit as a homeowner?

The City’s Residential Permits page says homeowners must use licensed trade contractors for new electrical work, and electrical permits are listed under trade contractors. Ask DSD at 210-207-1111 if you think you qualify for an exception.

How much does the permit cost?

The FY 2027 fee schedule lists generator fees of $1.84 (1–5 kW), $3.74 (6–50 kW), $5.58 (51–300 kW) and $7.48 (over 301 kW), plus a $57.50 electrical base fee and 4% + 4% surcharges. Ask DSD for the exact total for your job.

Does CPS Energy have to approve my generator?

IB 250 says back-up generator applications go to CPS Energy at [email protected], CPS approval is preferred first, and commissioning requirements must be met before use.

What is third-party review?

Under Texas SB 1202, IB 250 allows a qualified master electrician, electrical inspector or engineer, independent of the installer, to review plans and inspect home backup power systems. DSD says it responds to the submitted declarations within two business days.

Official sources

Every factual claim on this page is drawn from the government pages below, last checked on the date shown. If a link has moved, start at the AHJ website.

  1. City of San Antonio DSD — IB 250: Third Party Plan Review and Inspection of Back-up Systems (revised October 1, 2026) — accessed November 28, 2026; https://docsonline.sanantonio.gov/FileUploads/DSD/IB250.pdf
  2. City of San Antonio — FY 2027 Development Fee Schedule (revised October 2026) — accessed November 28, 2026; https://docsonline.sanantonio.gov/DSDUploads/CurrentFeeSchedule.pdf?title=Fee+Schedule+PDF
  3. City of San Antonio — Residential Permits — accessed November 28, 2026; https://www.sa.gov/Directory/Departments/DSD/Constructing/Residential/Permits
  4. City of San Antonio — DSD Electrical contractor registration — accessed November 28, 2026; https://www.sa.gov/Directory/Departments/DSD/Contractor/Electrical
  5. City of San Antonio — BuildSA Online Services — accessed November 28, 2026; https://www.sa.gov/Directory/Departments/DSD/BuildSA
  6. City of San Antonio — Electrical Permit Application — accessed November 28, 2026; https://docsonline.sanantonio.gov/FileUploads/dsd/DSD_Electrical_Application.pdf
  7. City of San Antonio — Citizen Access User Guide — accessed November 28, 2026; https://docsonline.sanantonio.gov/DSDUploads/CitizenAccessUserGuide.pdf
  8. CPS Energy — Distributed Generation — accessed November 28, 2026; https://www.cpsenergy.com/content/corporate/en/construction-and-renovation/distributed-generation.html
  9. Texas Department of Licensing and Regulation — Electricians — accessed November 28, 2026; https://www.tdlr.texas.gov/electricians/

Need a licensed electrician?

Most electrical permits still end with a licensed electrician doing the work — or at least signing off on an inspection. When referral programs are activated, the buttons below will go to those partners. Until then, hire a licensed electrician who is registered with the local AHJ, and verify their license with the state licensing board.

Angi

Homeowner-to-pro quotes for electrical work, including panel upgrades, EV chargers, and generator hookups.

Referral pending

Modernize

Pay-per-lead contractor matching for home-improvement trades. Modernize also sells generator leads to contractors (install, hookup, transfer switch).

Referral pending

Local licensed contractor

A reserved slot for a direct referral agreement with a licensed electrical contractor who already works in this jurisdiction.

Ready to activate